Find (a) The AOA network and the critical path. (b) All event slacks. (c) Critical path to
Question:
(a) The AOA network and the critical path.
(b) All event slacks.
(c) Critical path to event D.
(d) Critical path probability of completion in 14 days.
(e) The effect if CD slips to 6 days; to 7 days; to 8days.
Transcribed Image Text:
b-9763868017 m-6433205414 a-3103202411 EDEFE
Fantastic news! We've Found the answer you've been seeking!
Step by Step Answer:
Answer rating: 50% (16 reviews)
a The critical path is AC CB BE EF b The only event with slack is D at 3 days c If D were t...View the full answer
Answered By
Talha Talib
I am a member of IEEE society. As i am a student of electrical engineering badge 17 but beside of this i am also a tutor in unique academy. I teach calculus, communication skills, mechanics and economics. I am also a home tutor. My student Muhammad Salman Alvi is a brilliant A-level student and he performs very well in academics when i start to teach him. His weak point was mathematics but now he is performing well in mathematics. I am a scholarship holder in Fsc as i scored 1017 marks in metric out of 1100. Later on i got scholarship in Punjab Group of Colleges. I got 2nd position in robotics competition in 2018 as my project home automation select for the exhibition in Expocentre.
4.60+
23+ Reviews
62+ Question Solved
Related Book For
Project Management A Managerial Approach
ISBN: 978-0470226216
7th Edition
Authors: Jack R. Meredith, Samuel J. Mantel,
Question Posted:
Students also viewed these Management Leadership questions
-
Find a, b, c and d if (a) (b) (c) (d) a b b-c 3 1 2 2
-
If the probability that an event E occurs is 3 7, what are the odds that (a) E will occur? (b) E will not occur?
-
C and D are equal partners in the CD partnership. C starts the year with an adjusted basis of $300 in his partnership interest while D starts the year with an adjusted basis of $600. The partnership...
-
Use the Ratio Test to determine the values of x 0 for which each series converges. 00 X' k=0
-
Seneca Co. began year 2016 with 6,500 units of product in its January 1 inventory costing $35 each. It made successive purchases of its product in year 2016 as follows. The company uses a periodic...
-
Discuss the importance of a website's appearance.
-
What are the three basic items all motions must include?
-
Identify a process that you encounter on a daily basis, such as the lunch cafeteria or the journey from your home to school / work. What are the bottlenecks that limit the through put of this...
-
Karak Company produces Product (A) for only domestic distribution since year 2017. In 2019, a similar product to Karak Company has come onto the market by another competitor. Karak Company is keen to...
-
A 450-mm-long AISI 1020 steel rod is subjected to a tensile load of 55 kN. The allowable tensile stress is 140 MPa and the allowable total elongation is not to exceed 0.2 mm. Calculate the required...
-
Given the estimated activity times below and the network in Problem 8 above, what is the critical path probability that the project will be completed within: (a) 21 days? (b) 22 days? (c) 25days?...
-
a. Draw the AOA diagram. b. Find the critical path. c. Find the completion time. Activity TE AB .....1 AC .....2 AD .....3 DC .....4 CB .....3 DE .....8 CF .....2 BF .....4 IJ .......2 CE .....6 EF...
-
Japan and Germany have saving rates that are substantially higher than the U.S. As a result, they have accumulated more capital. On a per capita basis, Japan has about 22 percent more invested...
-
How does the program below demonstrate abstraction? b. If the keyword abstraction were deleted from line 2 would the program still compile? If C. it compiles, does it produce the same output? If the...
-
what ways does the concept of the "unreliable narrator" contribute to narrative complexity and reader engagement in postmodern literature? Cite specific examples from prominent works in the genre .
-
You are assigned to check whether the relative version of the purchasing power parity holds. Using data provided to you for the period 1971-2021 (see Excel file), prepare a brief report on the...
-
At April 30, partners' capital balances in DES Company are: Dexter $44,000. Emley $26,000, and Sigle $24,000. The income-sharing ratios are 5:3:2, respectively. On May 1, the DESW Company is formed...
-
A flat plate with surface area of 4.4 m is sliding on a horizontal table with 4.5 mm thick oil layer on top. Force applied on the plate in the direction of movement is 5.2 N. Dynamic viscosity of the...
-
Brian McGarrigle went to Les Arcs for his annual winter vacation. Unfortunately, he suffered a broken ankle while skiing and had to spend two days at the Hpital de Grasse. McGarrigles insurance...
-
Determine the values of the given trigonometric functions directly on a calculator. The angles are approximate. tan 0.8035
-
An insurance company in Asia reported profit of $100 million for the financial year through the news-dissemination system of the stock exchange. Its stock price increased several times, as the...
-
Explain how useful each of the following can be during the estimating of project costs: a. Contingency planning and estimating b. Using historical databases c. Usefulness of computer estimating d....
-
On June 12, 2002, Delta Corporation was awarded a $160,000 contract for testing a product. The contract consisted of $143,000 for labor and materials, and the remaining $17,000 was profit. The...
-
Acme Corporation has received a contractual order to build a new tooling machine for Alpha Corporation. The project started several months ago. Table 1514 is the Monthly Cost Summary for June, 2002....
-
Example of 2 business determine their 1.Main Products, joint products (if any), by Products. 2.What accounting method do you think is the most appropriate for the allocation of joint costs and for...
-
Small Ltd bought a 30% interest in a joint venture, Fry Ltd, for $50 000, on 1 July 2017. The equity of Fry Ltd at the acquisition date was: All the identifiable assets and liabilities of Fry Ltd...
-
Information given for question work in process inventory: beginning balance = 916,650 direct material = 589,670 direct labor = 159,600 applied overhead = 127,680 direct labor in beginning work in...
Study smarter with the SolutionInn App