Three alternatives are being considered. Alternative A has a useful life of 5 years; Alternative B, 6
Question:
Three alternatives are being considered. Alternative A has a useful life of 5 years; Alternative B, 6 years; and Alternative C, 8 years. Using the least-common-multiple approach, what is the planning horizon?
a. 30 years
b. 48 years
c. 120 years
d. 240 years