An order for 250 bell ringers is processed on work centers 10 and 20. The setup and
Question:
An order for 250 bell ringers is processed on work centers 10 and 20. The setup and run times are as follows. It is decided to overlap the lot on the two work centers and to split the lot into two lots of 100 and 150. Move time between operations is 30 minutes. Work center 20 cannot be set up until the first lot arrives. Calculate the saving in manufacturing lead time.
Setup on A = 50 minutes................Run time on A = 5 minutes per piece
Setup on B = 100 minutes.............Run time on B = 7 minutes per piece
Fantastic news! We've Found the answer you've been seeking!
Step by Step Answer:
Related Book For
Introduction To Materials Management
ISBN: 978-9386873248
8th edition
Authors: Arnold J. R. Tony, Gatewood Ann K., M. Clive Lloyd N. Chapman Stephen
Question Posted: