A certain project activity has a total slack of 0 days. If this activity gets delayed by
Fantastic news! We've Found the answer you've been seeking!
Question:
A certain project activity has a total slack of 0 days. If this activity gets delayed by 3 days, the project finish date will get delayed by? 1, 2, 3, or 0 days?