A computer-system installation project consists of eight activities. The immediate predecessors and activity times in weeks are
Fantastic news! We've Found the answer you've been seeking!
Question:
A computer-system installation project consists of eight activities. The immediate predecessors and activity times in weeks are shown below.
Activity | Immediate Predecessor | Activity Time |
A | - | 3 |
B | - | 6 |
C | A | 2 |
D | B, C | 5 |
E | D | 4 |
F | E | 3 |
G | B, C | 9 |
H | F, G | 3 |
Construct an early-start-date Gantt chart for the computer-system installation project.
As a project manager, where would you focus your attention, given your analysis?