The following project is at the end of its 6 th week. Find the cost and schedule
Fantastic news! We've Found the answer you've been seeking!
Question:
The following project is at the end of its 6 th week. Find the cost and schedule variances. Also find the CPI and SPI. Then find the critical ratio of the project using earned value calculations. Finally, calculate the ETC and EAC for the project.