The Spanish Navy Pays Nearly $3 Billion for a Submarine That Will Sink Like a Stone...
Fantastic news! We've Found the answer you've been seeking!
Question:
Transcribed Image Text:
The Spanish Navy Pays Nearly $3 Billion for a Submarine That Will Sink Like a Stone In 2003, shipbuilders at Navantia, Spain's state- owner shipyard, welcomed a contract from their navy to construct four state-of-the-art submarines. The S-80 class was going to be an engineering mar- vel, filled with the latest and most cutting-edge technology, including a diesel-electric propulsion system that would be 20% lighter than other ships, while delivering 50% more power. As the list of up- grades and new technical gadgetry grew, the deliv- ery date for the Isaac Peral-the lead ship in the S-80 class-continued to ship further behind schedule. Nevertheless, it wasn't the continuous upgrading and addition of new equipment that finally slammed the brakes on the project; it was the startling warning from Navantia's engineers that the Isaac Peral was not seaworthy. The submarine, named in honor of the Spanish man credited by some as the inventor of the underwater vessel, was 75-100 tons overweight, an excess that could make it difficult or impossible for the submarine to surface after submerging. As a re- sult, the Spanish navy was faced with the challenge of fixing a submarine that ran the risk of disaster whenever it decided to submerge! Navantia admitted the existence of "devia- tions related to the balance of weight" in the vessel and estimated it would take up to two years more to correct the problem, pushing the new delivery date to late 2018. The firm's engineers are trying to determine their best options at this point. It appears that two choices are most likely: Find a way to trim the design of the overall ship, which would be very difficult at this stage in construction, or lengthen the hull of the already 233-foot submarine to com- pensate for the extra weight. The problem with this option is that designers have estimated that for every meter the hull is lengthened, it will end up costing nearly 10 million additional euros (about $14 million dollars). Unfortunately for the Spaniards, indepen- dent agencies report that they have already sunk the equivalent of $680 million into the Isaac Peral, and a total of $3 billion into the entire quartet of S-80 class submarines. reactor is also underperforming. A Strategic Studies Group spokesperson said that the AlIP system has been designed to enable the submarine to operate underway for 28 days but is currently able to man- age only one week. The Group's memo suggests, "The buoyancy problem alone could cost up to half a billion euros to cover redesign and extra construc- tion, without considering the propulsion problem." The submarine setback couldn't have come at a worse time for Prime Minister Mariano Rajoy, who was already caught up in a corruption scan- dal and saw his approval rating hit a record low in 2013. Because of the poor shape of Spain's economy, Rajoy's austerity cuts trimmed the Spanish military budget by 30 percent in 2012, leaving much less room for added ballast. With reports that the S-80 program will be delayed an estimated two years and another general election looming in 2015, Rajoy likely will not see the submarines through to suc- cessful launch. How did such an expensive project get funded at a time when the Spanish military's entire special weap- ons program received a 98% cut? Sheer pride seems to have been a factor: Spain hoped the S-80 class would be a new homegrown breakthrough achieved with- out foreign help. Now that Navantia has entered into a $15 million contract with the Electric Boat Division of America's General Dynamics to help with the rede- sign, that dream seems dead in the water.17 Questions 1. Google "Spain's S-80 class submarine" and read some of the articles posted. In your opinion, how does technical risk cause problems with major defense projects? 2. Why do you think it is common for defense con- tractors to add new features and modifications to current programs? In other words, why do defense agencies contract for one project, only to see it often evolve into something new by the time it is launched? 3. If you were an advisor brought in by the Spanish government, what advice would you offer them in managing their defense projects? The buoyancy problem is not the only difficulty facing the program; an analyst said that that sub- marine's air-independent propulsion (AIP) system The Spanish Navy Pays Nearly $3 Billion for a Submarine That Will Sink Like a Stone In 2003, shipbuilders at Navantia, Spain's state- owner shipyard, welcomed a contract from their navy to construct four state-of-the-art submarines. The S-80 class was going to be an engineering mar- vel, filled with the latest and most cutting-edge technology, including a diesel-electric propulsion system that would be 20% lighter than other ships, while delivering 50% more power. As the list of up- grades and new technical gadgetry grew, the deliv- ery date for the Isaac Peral-the lead ship in the S-80 class-continued to ship further behind schedule. Nevertheless, it wasn't the continuous upgrading and addition of new equipment that finally slammed the brakes on the project; it was the startling warning from Navantia's engineers that the Isaac Peral was not seaworthy. The submarine, named in honor of the Spanish man credited by some as the inventor of the underwater vessel, was 75-100 tons overweight, an excess that could make it difficult or impossible for the submarine to surface after submerging. As a re- sult, the Spanish navy was faced with the challenge of fixing a submarine that ran the risk of disaster whenever it decided to submerge! Navantia admitted the existence of "devia- tions related to the balance of weight" in the vessel and estimated it would take up to two years more to correct the problem, pushing the new delivery date to late 2018. The firm's engineers are trying to determine their best options at this point. It appears that two choices are most likely: Find a way to trim the design of the overall ship, which would be very difficult at this stage in construction, or lengthen the hull of the already 233-foot submarine to com- pensate for the extra weight. The problem with this option is that designers have estimated that for every meter the hull is lengthened, it will end up costing nearly 10 million additional euros (about $14 million dollars). Unfortunately for the Spaniards, indepen- dent agencies report that they have already sunk the equivalent of $680 million into the Isaac Peral, and a total of $3 billion into the entire quartet of S-80 class submarines. reactor is also underperforming. A Strategic Studies Group spokesperson said that the AlIP system has been designed to enable the submarine to operate underway for 28 days but is currently able to man- age only one week. The Group's memo suggests, "The buoyancy problem alone could cost up to half a billion euros to cover redesign and extra construc- tion, without considering the propulsion problem." The submarine setback couldn't have come at a worse time for Prime Minister Mariano Rajoy, who was already caught up in a corruption scan- dal and saw his approval rating hit a record low in 2013. Because of the poor shape of Spain's economy, Rajoy's austerity cuts trimmed the Spanish military budget by 30 percent in 2012, leaving much less room for added ballast. With reports that the S-80 program will be delayed an estimated two years and another general election looming in 2015, Rajoy likely will not see the submarines through to suc- cessful launch. How did such an expensive project get funded at a time when the Spanish military's entire special weap- ons program received a 98% cut? Sheer pride seems to have been a factor: Spain hoped the S-80 class would be a new homegrown breakthrough achieved with- out foreign help. Now that Navantia has entered into a $15 million contract with the Electric Boat Division of America's General Dynamics to help with the rede- sign, that dream seems dead in the water.17 Questions 1. Google "Spain's S-80 class submarine" and read some of the articles posted. In your opinion, how does technical risk cause problems with major defense projects? 2. Why do you think it is common for defense con- tractors to add new features and modifications to current programs? In other words, why do defense agencies contract for one project, only to see it often evolve into something new by the time it is launched? 3. If you were an advisor brought in by the Spanish government, what advice would you offer them in managing their defense projects? The buoyancy problem is not the only difficulty facing the program; an analyst said that that sub- marine's air-independent propulsion (AIP) system
Expert Answer:
Answer rating: 100% (QA)
1 The technical risks associated with major defense projects are that the defense projects are always evolved with a theoretical assumption which when ... View the full answer
Related Book For
Fundamentals of Physics
ISBN: 978-0471758013
8th Extended edition
Authors: Jearl Walker, Halliday Resnick
Posted Date:
Students also viewed these general management questions
-
A vessel is filled with gas at some equilibrium pressure and temperature. Can all gas molecules in the vessel have the same speed?
-
A vessel is filled with gas at some equilibrium pressure and temperature. Can all gas molecules in the vessel have the same speed?
-
A man standing on the edge of a swimming pool looks at a stone lying on the bottom. The depth of the swimming pool is equal to h. At what distance from the surface of water is the image of the stone...
-
1. What velocity will a 300 kg snowmobile acquire if pushed from rest by a force of 6240 N [E] for 1.25 s? What average force will stop this snowmobile from moving at this speed in 1.25 s? (v = 26.0...
-
Rank the mass of these molecules from most to least. H. H. (. B A
-
1) The element to which specific style rules in a style sheet apply is a declaration. True False 2)MIME is a protocol that originally developed to allow different________ to be transmitted as...
-
Indicate whether the actions listed a through \(h\), primarily represent initiatives for cost containment (CC), cost avoidance (CA), or cost reduction (CR). Indicate what costs were contained,...
-
Aurora Company is considering the purchase of a new machine. The invoice price of the machine is $140,000, freight charges are estimated to be $4,000, and installation costs are expected to be...
-
A 6 0 - day Treasury bill has a bank discount yield of 3 . 2 5 % . What is the effective annual rate?
-
Southeastern Foods has hired you to analyze their distribution-system design. The company has 11 distribution centers, with monthly volumes as listed below. Seven of these sites can support...
-
Discuss the pros and cons of supporting the fixed exchange rate regimes in developing countries
-
To Garnishee (Receivables, Bank Accounts, Pay cheques, etc.) 1st: Swear and File an Affidavit in Support of Garnishee Summons 2nd: Obtain Garnishee Summons and serve 3 copies plus $25 upon the...
-
1)what is Array? 2)What is the difference b/w length and length() ? 3)What is Recursion? 4) What is Enum? 5) what is Wrapper classes?
-
Suez Canal was blocked for about six days in March 2021 as Ever Given, one of the largest container ships in the world, was stuck in the canal bank. This 2021 Suez Canal obstruction greatly affects...
-
Conduct research on the Internet to evaluate Facebook's Code of Conduct, accusations, issues, and corporate behavior from 2015 forward. Based on what you see here, how is Facebook in compliance or...
-
Create a Macro using the Macro recorder and Visual Basic statements that will do the following: 1. Create a macro recording the advanced Filter for just those employees located in Chicago Create a...
-
You expect to receive $4,200 upon your graduation and will invest your windfall at an interest rate of .65 percent per quarter until the account is worth $5,575. How many years do you have to wait...
-
Tanaka Company's cost and production data for two recent months included the following: March April Production (units).........300................600 Rent.....................$1,800............$1,800...
-
In Figure a uniform beam with a weight of 60 N and a length of 3.2m is hinged at its lower end, and a horizontal force F of magnitude 50 N acts at its upper end. The beam is held vertical by a cable...
-
A 10.0 g block with a charge of + 8.00 x 10-5 C is placed in an electric field E = (3000i 600j) N/C. What are the (a) Magnitude and (b) Direction (relative to the positive direction of the x axis)...
-
The magnetic field of a cylindrical magnet that has a pole-face diameter of 3.3 cm can be varied sinusoid ally between 29.6 T and 30.0 T at a frequency of 15 Hz. At a radial distance of 1.6 cm, what...
-
Refer to the Action feature, Channel Stuffing, on page 19. Suppose that performance bonuses based on revenues were eliminated and this behavior ceases. Would you favor eliminating performance-based...
-
Refer to the Action feature, Palliative Care Unit, on page 5. What type of costs in a hospital might be difficult to split between the PCU and non-PCU areas? What type of costs would be easy to...
-
Place the letter of the appropriate accounting cost in Column 2 in the blank next to each decision category in Column 1. Column 1 Analyzing executive performance Determining whether to produce...
Study smarter with the SolutionInn App