- Do some research and identify a complex project of your choice that might face duration challenges. Using your understanding of the readings this week, describe the advantages and disadvantages of reducing the project scope to accelerate the project and how you might reduce these disadvantages.
- The following table is an activity list that includes the duration and predecessor for a series of project activities. Draw a schedule network diagram and calculate the duration of the critical path.
Activity | Duration | Predecessor |
---|---|---|
A | 2 | Start |
B | 4 | A, E |
C | 6 | A |
D | 3 | B, C |
E | 7 | Start |
F | 2 | E |
End | - | D, F |