Marbles Company has the following information available regarding its labor: Managers expected to pay $11 per direct
Fantastic news! We've Found the answer you've been seeking!
Question:
Marbles Company has the following information available regarding its labor: Managers expected to pay $11 per direct labor hour, but ended up paying $10 per labor hour. Each unit produced should take 1 direct labor hour; actual total usage was 990 direct labor hours. Finally, the company planned to produce 1,000 units, but only produced 950. Calculate the labor activity variance.