On January 1, Year 1, Chester Co. began construction of a small building. The following expenditures were
Fantastic news! We've Found the answer you've been seeking!
Question:
On January 1, Year 1, Chester Co. began construction of a small building. The following expenditures were incurred for construction in Year 1: January 1 $125,000 May 1 $104,000 Oct 1 $124,000 December 31 $200,000 The building was not completed in Year 1. On January 1, Year 2, Chester spent another $180,000 on construction. The building was then completed and occupied on January 31, Year 2. To help pay for construction, $80,000 was borrowed on January 1, Year 1 on a 15%, three-year note payable. The entire $80,000 debt will remain outstanding until Year 4. Chester has no other debt. Calculate the weighted-average accumulated expenditures for Year 2.
Related Book For
Intermediate accounting
ISBN: 978-0077647094
7th edition
Authors: J. David Spiceland, James Sepe, Mark Nelson
Posted Date: