Question content area Part 1 In the following table the activities with their precedence sequence and expected
Fantastic news! We've Found the answer you've been seeking!
Question:
Question content area
Part 1
In the following table the activities with their precedence sequence and expected time (days) are listed for a project:
Activity | Immediate Predecessor(s) | Time (days) |
A | 7 | |
B | A | 2 |
C | A | 4 |
D | B | 5 |
E | B | 5 |
F | C | 5 |
G | E, F | 2 |
H | D | 3 |
I | G, H | 5 |
a) The activities on the critical path are ______________. (A-C-F-G-I, A-B-E-G-I, or A-B-D-H-I)
b) The project length is _______ days.