The Widget Maker Company is bidding for a new job that requires building four widget prototypes....
Fantastic news! We've Found the answer you've been seeking!
Question:
Transcribed Image Text:
The Widget Maker Company is bidding for a new job that requires building four widget prototypes. The company has never built the particular widget before, but its experts believe that its designers and workers will be able to pick it up with a learning rate of 80%. The activity of designing and building prototypes will gain from this learning rate for at least five cycles. The proposal team has come up with the following action plan and effort estimates for producing the four units. S. No. Task 1 2 3 4 5 6 7 8 9 10 11 12 13 14 Effort in hrs Precedence 36 18 Concept development Design framework Design and build first prototype Ship to customer Analyze feedback Design and build second prototype Ship to customer Analyze feedback Design and build third prototype Ship to customer Analyze feedback Design and build final prototype 46.1 Ship to customer 3.6 Update customer design knowledge base 18 72 3.6 14.4 57.6 3.6 14.4 50.6 3.6 14.4 1FS 2FS 3FS 4FS+2 weeks lag 3FS 6FS 7FS+2 weeks lag 5FS, 6FS 9FS 10FS+2weeks lag 8FS, 9FS 12FS 11FS, 13FS The company plans its work assuming a 90% efficiency of its staff members. Task 2, Design framework, and Task 14, Update design knowledge base, require an expert designer who is available only 50% of the time due to other commitments. The company has an average labor rate of $50/hour. The benefit rate is 30%. Its overhead costs are 50% and its profit margin is 20%. The project plans are to be developed assuming 8 hours per working day and 5 working days per week. A. Provide a table with estimated durations for each task taking efficiency and availability in consideration where applicable. Please round to the nearest tenth of an hour. (30 points) HINT: provide a table with a column for allocated hr (efficiency) and a column for total task duration hr for each task. B. What is the total project duration in calendar weeks and completion date that the company should propose? Assume a start date of Monday, 6 February 2023, and that the company believes its estimates already are generous and no additional time buffer is needed. (10 points) C. What is the amount that the company should bid for this project? (10 points) The Widget Maker Company is bidding for a new job that requires building four widget prototypes. The company has never built the particular widget before, but its experts believe that its designers and workers will be able to pick it up with a learning rate of 80%. The activity of designing and building prototypes will gain from this learning rate for at least five cycles. The proposal team has come up with the following action plan and effort estimates for producing the four units. S. No. Task 1 2 3 4 5 6 7 8 9 10 11 12 13 14 Effort in hrs Precedence 36 18 Concept development Design framework Design and build first prototype Ship to customer Analyze feedback Design and build second prototype Ship to customer Analyze feedback Design and build third prototype Ship to customer Analyze feedback Design and build final prototype 46.1 Ship to customer 3.6 Update customer design knowledge base 18 72 3.6 14.4 57.6 3.6 14.4 50.6 3.6 14.4 1FS 2FS 3FS 4FS+2 weeks lag 3FS 6FS 7FS+2 weeks lag 5FS, 6FS 9FS 10FS+2weeks lag 8FS, 9FS 12FS 11FS, 13FS The company plans its work assuming a 90% efficiency of its staff members. Task 2, Design framework, and Task 14, Update design knowledge base, require an expert designer who is available only 50% of the time due to other commitments. The company has an average labor rate of $50/hour. The benefit rate is 30%. Its overhead costs are 50% and its profit margin is 20%. The project plans are to be developed assuming 8 hours per working day and 5 working days per week. A. Provide a table with estimated durations for each task taking efficiency and availability in consideration where applicable. Please round to the nearest tenth of an hour. (30 points) HINT: provide a table with a column for allocated hr (efficiency) and a column for total task duration hr for each task. B. What is the total project duration in calendar weeks and completion date that the company should propose? Assume a start date of Monday, 6 February 2023, and that the company believes its estimates already are generous and no additional time buffer is needed. (10 points) C. What is the amount that the company should bid for this project? (10 points)
Expert Answer:
Related Book For
Posted Date:
Students also viewed these general management questions
-
3 4 5 6 7 8 9 10 11 12 13 A 14 Cost of the Asset 15 Life of the Asset in Years 16 Book Value of the Asset after 5 years 17 Depreciable Basis 18 Yearly depreciation 19 After tax Salvage Value in year...
-
Year 1 2 3 4 5 6 7 A coal mining company is expanding its existing operation. The company expects that it will experience an increasing stripping ratio scenario in the expansion area, and with...
-
A 1 defects size B D E 88888888888888888888888888 2 21 3 24 4 16 5 12 6 15 7 5 8 28 9 20 10 31 11 25 12 20 13 24 14 16 15 19 16 10 17 17 18 13 19 22 20 18 21 39 22 30 23 24 24 16 25 19 26 17 27 15...
-
A solid conducting cylinder of radius 0.1 m and mass of 4 kg rests on horizontal conducting rails (Figure). The rails, separated by a distance a?= 0.4 m, have a rough surface so the cylinder rolls...
-
Give some examples of appropriate general journal transactions for an organization using special journals.
-
Calculate the relative humidity, the humidity ratio, and the partial pressure of the dry air if, for the atmospheric air: a) Tdb 5 20 8C, Tdp 5 15 8C, P atm 5 100 kPa b) Tdb 5 30 8C, Tdp 5 20 8C, P...
-
Key comparative figures ($ thousands) for both Krispy Kreme and Tastykake follow: Required Krispy Kreme Tastykake Current One Year Two Years Current Prior Prior Year One Year Prior $ 16,159 $ 12,031...
-
HJ. Heinz Company uses standards to control its materials costs. Assume that a batch of ketchup (1,500 pounds) has the following standards: The actual materials in a batch may vary from the standard...
-
11. The Coca Cola Company has 366,000 stockholders and a poll is conducted by randomly selecting 30 stockholders from each of the 50 states. The number of shares held by each sampled stockholder is...
-
Nucor Corporation produces steel and steel products at its eight mills and is a major recycler of scrap metal. The following data relate to Nucor for four years. In 2017, Nucors net income was higher...
-
Thirty randomly selected customers of Google's Grocery were given a produce knowledge test. The sample mean from this test was 85 and the sample standard deviation was 6.6. Construct a 99% confidence...
-
Determining the range of Q-point values for this circuit. www11 RG 1 MO Vos (V) -8 +10 V RD 500 0 2N5459 Rs 500 0 60 g lp (mA) T T T L T 16 14 12 10 8 6 4 2 Note: VGSX and IDX are not located on the...
-
what would the weighted average cost of capital be after the change in capital structure if the corporate tax rate was 15% instead of 35%
-
sandy samuelson, the CFO of tempe based company, sates, is planning to raise $50,000,000 on wall street by selling bonds. each bond will have a par value of $1000, a coupon rate of 13% and a maturity...
-
The inventory for Target over last three years was 403 in 2022, (3249) in 2021, and (1661) in 2020 (United States Securities and Exchange Commission, 2023). Inventory uses LIFO method, states...
-
1. If a slender bar rotates about end A, its angular momentum with respect to A is A) (1/12) m 1 o B) (1/6) m 1 o C) (1/3) m 1 o D) m 1 w 2. As in the principle of work and energy, if a force does no...
-
Required Information [The following information applies to the questions displayed below] Beech Corporation is a merchandising company that is preparing a master budget for the third quarter of the...
-
If someone's Z-score for a variable was 0.67. Their score is a significant extreme score. Their score is not significant. O Their score is slightly above average. O Their score is an outlier.
-
People like to have a stable living standard from one year to the next. Yet studies show that the level of consumption drops suddenly, predictably, and significantly at retirement (contrary to Figure...
-
Consider a bond with a face value of $1000 and a coupon of $100. Suppose the interest rate is 10 percent. Does the PDV of the promised payments depend on the bond's maturity? Why or why not? Think...
-
Suppose a single monopolist controls the market for Coke and Pepsi in Worked-Out Problem 19.2. If the monopolist sets the same price for Coke and Pepsi, what price would maximize its profit? How does...
-
Cubs Incorporated manufactures a product with a selling price of $60 per unit. Units and monthly cost data follow: Cubs Inc. pays all bills in the month incurred. All sales are on account with 50...
-
Matt Albin, Ryan Peters, and Seth Ramsey invested $82,000, $49,200, and $32,800, respectively, in a partnership. During its first calendar-year, the firm earned $135,000. Required Prepare the entry...
-
Required Continuing problem P9-40, management is concerned that their supplier of raw materials will have a strike. Determine the budget implications if management plans to increase the January-end...
Study smarter with the SolutionInn App