a. Draw the AOA diagram. b. Find the critical path. c. Find the completion time. Activity
Question:
a. Draw the AOA diagram.
b. Find the critical path.
c. Find the completion time.
Activity †TE
AB .....1
AC .....2
AD .....3
DC .....4
CB .....3
DE .....8
CF .....2
BF .....4
IJ .......2
CE .....6
EF .....5
FG .......10
FH .......11
EH .....1
GH .....9
EJ .....3
GI .....8
HJ.....6
Transcribed Image Text:
mes Optimistic Most Likely Pesimistic Preceding Tasks 1 Lay foundation 2 Dig hole for scale 3 Insert scale bases 4 Erect frame 5 Complete building 6 nsert scales 7 Insert display cases 8 Put in office equipment 9 Finishing touches 10 13 21 30 13 10 15 12 20 4 10
Fantastic news! We've Found the answer you've been seeking!
Step by Step Answer:
Answer rating: 85% (14 reviews)
a b The critical path is ...View the full answer
Answered By
Lisper Wanja
I am an experienced and highly motivated writer with a passion for the skills listed. I have a proven track record of my expertise and my aim is to deliver quality, well-detailed and plagiarism free projects. My genuine passion for writing combined with my ongoing professional development through school and research makes me an ideal candidate within for any assignment.
4.90+
233+ Reviews
388+ Question Solved
Related Book For
Project Management A Managerial Approach
ISBN: 978-0470226216
7th Edition
Authors: Jack R. Meredith, Samuel J. Mantel,
Question Posted:
Students also viewed these Management Leadership questions
-
For the data as follows, draw the AOA diagram and identify the critical path. What is the length of the critical path? Activity Immediate Predecessors Days A - 5 B A 2 C A 4 D B 5 E B 4 F C 4 G E, F...
-
Draw a path diagram with three exogenous constructs and one endogenous construct. The exogenous constructs are measured by 5. 4. and 3 observed variables or indicators. The endogenous construct is...
-
Find the critical path for the following project (task times are in weeks): Task Preceding Tasks A None 11 14 10 12 DIB 8 9 E C, D
-
Find the values of the parameter p > 0 for which the following series converge. k=1 k ^ ( + In k + 1/ P
-
Hallam Company's financial statements show the following. The company recently discovered that in making physical counts of inventory, it had made the following errors: Inventory on December 31,...
-
Carnival Corporation is the largest cruise company in the world. The following item appears in the current liabilities section of its balance sheet included in the Form 10-K for the year ended...
-
The expected activity of the paper-making plant of Leventhal Paper Company was 45,000 machine hours per month. Practical capacity was 60,000 machine hours per month. The standard machine hours...
-
The fermentation of corn produces a mixture of 3.3 mol% ethyl alcohol in water. If 20 mol% of this mixture is distilled at 1atm by a simple, batch distillation, calculate and plot the...
-
gangster movies on TV, you often hear of "number runners" or the "numbers racket." This numbers game, which is still played today, involves betting $1 on the last three digits of the number of sold...
-
Companies that sell luxury goods, such as Chanel, Pres les, Le Morgan, have been offering their products for sale on their Web sites for many years. These businesses preferred to use their Web sites...
-
Find (a) The AOA network and the critical path. (b) All event slacks. (c) Critical path to event D. (d) Critical path probability of completion in 14 days. (e) The effect if CD slips to 6 days; to 7...
-
The Denver Iron & Steel Company is expanding its operations to include a new drive-in weigh station. The weigh station will be a heated/air-conditioned building with a large floor and small office....
-
Many familiar substances have common, unsystematic names. For each of the following, give the correct systematic name: (a) Saltpeter, KNO3; (b) Soda ash, Na2CO3 (c) Lime, CaO (d) Muriatic acid, HCl...
-
A key element of the COSO ERM model is risk appetite. Risk appetite is a. Best determined by management with board of director review and concur- rence. b. An integral part of the risk culture. c. A...
-
Explain why it may be easier for the auditor to assess environment risk as opposed to separately assessing inherent risk and control risk.
-
What are the major advantages to a company of implementing an effective enterprise risk management process?
-
What are the eight elements of the COSO ERM model? Explain each component and its importance to effective enterprise risk management.
-
How might an organization go about sharing or transferring risk?
-
What are BOs that make up the reputation pattern?
-
Differentiate. y = ln(3x + 1) ln(5x + 1)
-
Which of the following causes the majority of computer security problems? a. Human errors b. Software errors c. Natural disasters d. Power outages
-
In a status report, executives want to know not only where we are today, but also where we will end up. Calculating where we will end up financially is not as easy as it sounds. Selecting the wrong...
-
A homeowner hires a contractor to build a four-sided square fence around his home. The homeowner provides the materials and the contractor supplies the labor. The contractor estimates each side will...
-
Your company has asked you to determine the financial risks of manufacturing 6,000 units of a product rather than purchasing them from a vendor at $66.50 per unit. The production line will handle...
-
Required information [The following information applies to the questions displayed below] Project Y requires a $336,000 investment for new machinery with a six-year life and no salvage value. The...
-
Exercise 17-5 (Algo) Product mix and plantwide rate versus activity-based costing LO P1, P3 Wess Company has limited capacity and can produce either its standard product or its deluxe product....
-
Check m Comparative financial statements for Weller Corporation, a merchandising company, for the year ending December 31 appear below. The company did not issue any new common stock during the year....
Study smarter with the SolutionInn App