A two-person shoe repair operation uses a two-step sequence that all jobs follow (first work centre A
Question:
a. Find the sequence that will minimize tire make-span.
b. Determine the amount of idle time for work centre B.
c. What jobs are candidates for splitting? Why? If jobs b and c are split in half, how much would tire idle time for work centre B be reduced?
Transcribed Image Text:
Job Times (minutes) 15 26 24 18 Work Centre A Work Centre B 27 45 70 30
Fantastic news! We've Found the answer you've been seeking!
Step by Step Answer:
Answer rating: 58% (17 reviews)
a Job WC A WC B a 27 4 45 Circles show order of assi...View the full answer
Answered By
JAPHETH KOGEI
Hi there. I'm here to assist you to score the highest marks on your assignments and homework. My areas of specialisation are:
Auditing, Financial Accounting, Macroeconomics, Monetary-economics, Business-administration, Advanced-accounting, Corporate Finance, Professional-accounting-ethics, Corporate governance, Financial-risk-analysis, Financial-budgeting, Corporate-social-responsibility, Statistics, Business management, logic, Critical thinking,
So, I look forward to helping you solve your academic problem.
I enjoy teaching and tutoring university and high school students. During my free time, I also read books on motivation, leadership, comedy, emotional intelligence, critical thinking, nature, human nature, innovation, persuasion, performance, negotiations, goals, power, time management, wealth, debates, sales, and finance. Additionally, I am a panellist on an FM radio program on Sunday mornings where we discuss current affairs.
I travel three times a year either to the USA, Europe and around Africa.
As a university student in the USA, I enjoyed interacting with people from different cultures and ethnic groups. Together with friends, we travelled widely in the USA and in Europe (UK, France, Denmark, Germany, Turkey, etc).
So, I look forward to tutoring you. I believe that it will be exciting to meet them.
3.00+
2+ Reviews
10+ Question Solved
Related Book For
Operations Management
ISBN: 978-0071091428
4th Canadian edition
Authors: William J Stevenson, Mehran Hojati
Question Posted:
Students also viewed these Management Leadership questions
-
A shoe repair operation uses a two- step sequence that all jobs in a certain category follow. All jobs can be split in half at both stations. For the group of jobs listed, a. Find the sequence that...
-
If a group of business assets is sold with specific values attached to each item, what difference, if any, does it make whether the terms of payment (that is, the amount of cash and deferred...
-
The times required to complete each of eight jobs in a two-machine flow shop are shown in the table that follows. Each job must follow the same sequence, beginning with machine A and moving to...
-
Problem 10 The Solow Growth Model is an exogenous model of economic growth that analyzes changes in the level of output in an economy over time as a result of changes in the population growth rate,...
-
A chemical brearhalyzer test works because ethyl alco¬hol in the breath is oxidized by the dichromate ion (orange) to form acetic acid and chromium(III) ion (green). The balanced reaction is You...
-
Which of the following operators are Hermitian: d/dx, id/dx, 4d2/dx2, id2/dx2? (See Prob. 7.6.)
-
Animation art, hand-painted images from which cartoons used to be made, is a popular collectible.
-
Lawrence Industries most recent annual dividend was $1.80 per share (D 0 = $1.80), and the firms required return is 11%. Find the market value of Lawrences shares when: a. Dividends are expected to...
-
Can someone help me to explain this paper ? i need a brief analysis please. Digby Annual Report Round 7 -2027 Round Sim ID ZP89810_1 Cash Flow Statement 2026 2027 Cash Flows from Operating activities...
-
The following trial balance was prepared for Tile, Etc., Inc. on December 31, Year 1, after the closing entries were posted: Account Title Cash ........................................................
-
Given the operation times below in a two-work-centre flow shop: a. Develop a job sequence that minimizes total idle time at the two work centres. b. Construct a Gantt chart for the activities at the...
-
The following schedules (in hours) were prepared by the production manager of a metal shop. Note that ail jobs first go through cutting, then polishing. Determine a sequence of jobs that will result...
-
Define audit data analytics.
-
The construction team is behind schedule on its project. The customer is considering giving the project to another company if the project cannot be put back on track. The team is considering putting...
-
The project to roll out tablets for use in a 500-bed hospital is going well, except for a minor problem in the MRI area, where the wireless access isnt working as expected. What documentation should...
-
The project to develop a vaccine against bee colony collapse is experiencing conflict. To minimize this, what tools are available to the project manager? a. Interpersonal skills, ground rules, and...
-
The expansion project requires extensive communication with stakeholders. On what will the project manager rely to determine what information should be communicated and who should receive the...
-
Of the following, which is the most comprehensive definition of monitoring and controlling? a. To monitor plan resources and make replacements as needed b. To check for variances from the plan and...
-
A coffee manufacturer wants to market a new blend of coffee that sells for $3.90 per pound by mixing two coffees that sell for $2.75 and $5 per pound, respectively.What amounts of each coffee should...
-
The Thomas Corporation was organized on Jan. 1, 2020. On Dec. 31, 2021, the corporation lost most of its inventory in a warehouse fire before the year-end count of inventory was to take place. just...
-
The following table provides the information necessary to construct a project network and project crash data: Construct the project network, and crash the network the maximum amountpossible. Activity...
-
The following table provides the information necessary to construct a project network and project crash data: Construct the project network, and crash the network the maximum amountpossible. Activity...
-
For the Solved Problem at the end of this chapter, assume that the most likely times (m) are the normal activity times and the optimistic times (a) are the activity crash times. Further assume that...
-
On November 1, 2023, Alan Company signed a 120-day, 10% note payable, with a face value of $63,000. Alan made a December 31 year-end accrual for interest earned. (Use 360 days a year.) 2a. Write the...
-
The trustees of a small college are considering voting a pay raise for their faculty members. They want to grant a 4 percent raise for those earning more than $70,000.00, a 7 percent raise for those...
-
i need help. 1- Write a code for a banking program. a) In this question, first, you need to create a Customer class, this class should have: 2 private attributes: name (String) and balance (double)...
Study smarter with the SolutionInn App