Curtiss Construction Company, Inc., entered into a fixed-price contract with Axelrod Associates on July 1, 2011, to

Question:

Curtiss Construction Company, Inc., entered into a fixed-price contract with Axelrod Associates on July 1, 2011, to construct a four-story office building. At that time, Curtiss estimated that it would take between two and three years to complete the project. The total contract price for construction of the building is $4,000,000. Curtiss appropriately accounts for this contract under the completed contract method in its financial statements. The building was completed on December 31, 2013. Estimated percentage of completion, accumulated contract costs incurred, estimated costs to complete the contract, and accumulated billings to Axelrod under the contract were as follows:


Curtiss Construction Company, Inc., entered into a fixed-price c


Required:
1. Prepare schedules to compute gross profit or loss to be recognized as a result of this contract for each of the three years.
2. Assuming Curtiss uses the percentage-of-completion method of accounting for long-term construction contracts, compute gross profit or loss to be recognized in each of the three years.
3. Assuming the percentage-of-completion method, compute the amount to be shown in the balance sheet at the end of 2011 and 2012 as either cost in excess of billings or billings in excess ofcosts.

Balance Sheet
Balance sheet is a statement of the financial position of a business that list all the assets, liabilities, and owner’s equity and shareholder’s equity at a particular point of time. A balance sheet is also called as a “statement of financial...
Fantastic news! We've Found the answer you've been seeking!

Step by Step Answer:

Related Book For  book-img-for-question

Intermediate Accounting

ISBN: 978-0077400163

6th edition

Authors: J. David Spiceland, James Sepe, Mark Nelson

Question Posted: