Doug Casey is in charge of planning and coordinating next springs sales management training program for his
Question:
Doug Casey is in charge of planning and coordinating next spring’s sales management training program for his company. Doug listed the following activity information for this project:
a. Draw a project network.
b. Prepare an activity schedule.
c. What are the critical activities and what is the expected project completion time?
d. If Doug wants a 0.99 probability of completing the project on time, how far ahead of the scheduled meeting date should he begin working on theproject?