As a plant engineer, you are testing a new drying procedure for the plant. Two options exist:
Fantastic news! We've Found the answer you've been seeking!
Question:
As a plant engineer, you are testing a new drying procedure for the plant. Two options exist: A and B. Option A is currently in place, while option B is a faster new method. The criterion for implementation is that the quality of the material being dried should not decrease by more than 0.1 at an = 0.05. This value has been determined based on a costbenefit analysis of the costs of drying compared with the costs of production. Determine if option B should be implemented.
Production quality,Option A Production quality, Option B
95.6 | 89.2 |
97.3 | 94.2 |
95.6 | 93.9 |
95.4 | 93.2 |
99.4 | 94.7 |
97.2 | 91.7 |
92.2 | 93.2 |
92.8 | 92.4 |
94.3 | 91.8 |
92.6 | 91.5 |
Posted Date: