In the following MRP planning schedule for Item J , indicate the correct net requirements, planned -
Fantastic news! We've Found the answer you've been seeking!
Question:
In the following MRP planning schedule for Item J indicate the correct net requirements, plannedorder receipts, and plannedorder releases to meet the gross requirements. Lead time is one week.
Note: Leave the cells blank, whenever zero is required.
ITEM J WEEK NUMBER
Gross requirements
Onhand
Net requirements
Plannedorder receipt
Plannedorder release