A 50-meter tunnel must be constructed as part of a new aqueduct system for a city. Two

Question:

A 50-meter tunnel must be constructed as part of a new aqueduct system for a city. Two alternatives are being considered. One is to build a full-capacity tunnel now for $500,000. The other alternative is to build a half-capacity tunnel now for $300,000 a na then to build a second parallel half-capacity tunnel 20 years hence for $400,000. The cost to repair the tunnel lining every 10 years is estimated to be $20,000 for the full-capacity tunnel and $16,000 for each half capacity tunnel. Determine whether the full-capacity tunnel or the half-capacity tunnel should be constructed now. Solve the problem by the conventional benefit-cost ratio analysis, using a 5% interest rate and a 50-year analysis period. There will be no tunnel lining repair at the end of the 50 years.