A company has budgeted for materials of 170,000 but the actual costs are 164,000. The company has

Question:

A company has budgeted for materials of £170,000 but the actual costs are £164,000. The company has also budgeted for labour of £130,000 with actual costs being £133,000. The expense variance is: b) £3,000 favourable
Fantastic news! We've Found the answer you've been seeking!

Step by Step Answer:

Question Posted: