Question: A company has gathered the following information from a recent production run: Standard variable overhead rate......... $10 Actual variable overhead rate .......... 8 Standard process
A company has gathered the following information from a recent production run:
Standard variable overhead rate......... $10
Actual variable overhead rate .......... 8
Standard process hours............. 20
Actual process hours............. 25
What is the company’s variable overhead spending variance?
a. $50 unfavorable
b. $50 favorable
c. $40 unfavorable
d. $40 favorable
Step by Step Solution
3.46 Rating (162 Votes )
There are 3 Steps involved in it
b Variable ... View full answer