A consulting firms accounting records show the following costs for year 1: Direct materials supplies . .

Question:

A consulting firm’s accounting records show the following costs for year 1:

Direct materials supplies . . . . . . . . . . . . . . $ 360,000

Direct labor . . . . . . . . . . . . . . . . . . . . . . . . 2,580,000

Total overhead . . . . . . . . . . . . . . . . . . . . . 1,140,000

Production was 150,000 billable hours. Fixed overhead was $600,000.

For year 2, direct materials costs are expected to increase by 10 percent per unit. Direct labor costs are expected to increase by 15 percent. Variable overhead per billable hour is expected to remain the same, but fixed overhead is expected to increase by 5 percent.


Required

a. Year 2 production is expected to be 195,000 billable hours. What are the estimated direct materials, direct labor, variable overhead, and fixed overhead costs for year 2?

b. Determine the total costs per billable hour for year 1 and year 2.

Fantastic news! We've Found the answer you've been seeking!

Step by Step Answer:

Related Book For  book-img-for-question

Fundamentals of Cost Accounting

ISBN: 978-0077398194

3rd Edition

Authors: William Lanen, Shannon Anderson, Michael Maher

Question Posted: