A contractor has estimated that the minimum number of days to remodel a bathroom for a client

Question:

A contractor has estimated that the minimum number of days to remodel a bathroom for a client is 10 days. He also estimates that 80% of similar jobs are completed within 18 days. If the remodeling time is uniformly distributed, what should be the parameters of the uniform distribution?