Question: A contractor intends to bid on a job installing 30 airport security systems. Because this will be a new line of work for the contractor,
A contractor intends to bid on a job installing 30 airport security systems. Because this will be a new line of work for the contractor, he believes there will be a learning effect for the job. After reviewing time records from a similar type of activity, the contractor is convinced that an 85 percent curve is appropriate. He estimates that the first job will take his crew eight days to install. How many days should the contractor budget for?
a. The first 10 installations?
b. The second 10 installations?
c. The final 10 installations?
Step by Step Solution
3.68 Rating (174 Votes )
There are 3 Steps involved in it
Given Job calls for installing 30 security systems Learning curve percentage 85 Estimate for first j... View full answer