A contractor intends to bid on a job installing 30 airport security systems. Because this will be

Question:

A contractor intends to bid on a job installing 30 airport security systems. Because this will be a new line of work for the contractor, he believes there will be a learning effect for the job. After reviewing time records from a similar type of activity, the contractor is convinced that an 85 percent curve is appropriate. He estimates that the first job will take his crew eight days to install. How many days should the contractor budget for?
a. The first 10 installations?
b. The second 10 installations?
c. The final 10 installations?

Fantastic news! We've Found the answer you've been seeking!

Step by Step Answer:

Related Book For  book-img-for-question

Operations Management

ISBN: 978-0078024108

12th edition

Authors: William J Stevenson

Question Posted: