A deep foundation engineering contractor has bid on a foundation system for a new building housing the
Question:
A deep foundation engineering contractor has bid on a foundation system for a new building housing the world headquarters for a Fortune 500 company.A part of the project consists of installing 311 auger cast piles. The contractor was given bid information for cost estimating purposes, which consisted of the estimated depth of each pile; however, actual drill footage of each pile could not be determined exactly until construction was performed. The Excel file Pile Foundation contains the estimates and actual pile lengths after the project was completed. Develop a linear regression model to estimate the actual pile length as a function of the estimated pile lengths. What do you conclude?
Fantastic news! We've Found the answer you've been seeking!
Step by Step Answer:
Related Book For
Question Posted: