A firm makes a basic scissors consisting of three parts: the left side, the right side, and
Question:
a. Assume the master schedule calls for 200 scissors to be shipped in week 4 and 500 in week 5; work out a complete materials plan.
b. Suppose the supplier of right-hand sides calls to say that deliveries of the 200 parts on order will be one week late. What effect will this have on the materials plan?
c. If demand for scissors is uncertain and has a standard deviation of 50 units, what would you recommend the firm do to maintain a 95 percent service level for scissors?
d. If the delivery of the scissors parts is unreliable and the standard deviation of delivery lead time is one week for each of the parts, what would you recommend the firm do to maintain its production schedule?
Step by Step Answer:
Operations Management in the Supply Chain Decisions and Cases
ISBN: 978-0073525242
6th edition
Authors: Roger Schroeder, M. Johnny Rungtusanatham, Susan Goldstein