A PERT problem is detailed in the table below. Times are given in weeks. a. Draw a

Question:

A PERT problem is detailed in the table below. Times are given in weeks.


A PERT problem is detailed in the table below. Times


a. Draw a network diagram using the AOA approach and identify all paths of the project.
b. What is the expected completion time of the project?
c. What are the project variance and the project standard deviation?
d. Determine all possible paths. Which path is critical?
e. Determine the probability that the project is completed within 48 weeks, assuming that the path identified in (b) iscritical.

Fantastic news! We've Found the answer you've been seeking!

Step by Step Answer:

Related Book For  book-img-for-question

Applied Regression Analysis And Other Multivariable Methods

ISBN: 632

5th Edition

Authors: David G. Kleinbaum, Lawrence L. Kupper, Azhar Nizam, Eli S. Rosenberg

Question Posted: