A process is designed to produce 500 units per hour with a scrap rate of 1% and

Question:

A process is designed to produce 500 units per hour with a scrap rate of 1% and inherent inefficiencies of 10%. Assuming that actual output is 425 units per hour, compute design capacity, available capacity, actual capacity, capacity utilization, efficiency, and output gap measure.