A production process uses a two- step operation. Tomorrows work wi11 consist of seven order s as

Question:

A production process uses a two- step operation. Tomorrow€™s work wi11 consist of seven order s as shown below. Determine a job sequence that will minimize the total time required to fill the orders (i.e., the make-span) and determine the make-span.