A project to remodel an office area has the following activities. (Hint: You will need to build

Question:

A project to remodel an office area has the following activities. (Hint: You will need to build an AIB/AON diagram, perform a forward pass, and perform a backward pass to answer this question.)

Activity Duration Predecessors 3 months 2 months 3 months 4 months A, B 3 months A. 2 months B, C 2 months 1 month Н G

a) What are the critical path activities?
b) What is the project's scheduled completion time?
c) What is the slack or float for Activity B? Show your calculations.
d) What is the slack or float for Activity C? Show your calculations.
e) What is the slack or float for Activity E? Show your calculations.
f) What is the slack or float for Activity H? Show your calculations.

Fantastic news! We've Found the answer you've been seeking!

Step by Step Answer:

Related Book For  book-img-for-question

Advanced Accounting

ISBN: 978-1259444951

13th edition

Authors: Joe Ben Hoyle, Thomas Schaefer, Timothy Doupni

Question Posted: