a. Refer to the table below. What is the cumulative budgeted cost at the end of week

Question:

a. Refer to the table below. What is the cumulative budgeted cost at the end of week 6?


Week TBC 3. 4 9. 10 Task 1 30 10 15 20 10 10 Task 2 10 10 70 Task 3 40 25 Task 4 20 30 Total 170 10 25 15 10 25 15 35 10


Amounts are in thousands of dollars.


b. Below is a table of actual costs. What is the cumulative actual cost at the end of week 6? Determine whether there is a cost overrun or under run. What is causing it?


a. Refer to the table below. What is the cumulative


Amounts are in thousands of dollars.


c. Below is a table of the cumulative percentages of work completed by the end of week 6. What is the cumulative earned value of the project at the end of week 6? Is it good?

a. Refer to the table below. What is the cumulative


Amounts are cumulative percentages complete.

d. What is the CPI at the end of week 6? What is the CV?

e. Calculate the FCAC using the first two methods described in the chapter. In addition, describe a third FCAC method you could use.

Fantastic news! We've Found the answer you've been seeking!

Step by Step Answer:

Related Book For  book-img-for-question

Successful Project Management

ISBN: 9780324656138

4th Edition

Authors: Jack Gido, Jim Clements

Question Posted: