A shop works a 400-minute day. The manager of tire shop wants an output rate of 200

Question:

A shop works a 400-minute day. The manager of tire shop wants an output rate of 200 units per day for the assembly line that has the tasks shown in the following table. Do the following:
a. Construct the precedence network and calculate the cycle time.
b. Assign tasks according to €œAssign the task with the most followers€ rule. In the case of a tie, use €œAssign tire task with the longest time€ heuristic rule.
c. Calculate the balance delay.
A shop works a 400-minute day. The manager of tire
Fantastic news! We've Found the answer you've been seeking!

Step by Step Answer:

Related Book For  book-img-for-question

Operations Management

ISBN: 978-0071091428

4th Canadian edition

Authors: William J Stevenson, Mehran Hojati

Question Posted: