A software development project at day 70 exhibits an actual cost of $78,000 and a scheduled cost

Question:

A software development project at day 70 exhibits an actual cost of $78,000 and a scheduled cost of $84,000. The software manager estimates a value completed of $81,000. What are the cost and schedule variances and CSI? Estimate the time variance.