A task is expected to take 20 hours of labor at $25 per hour (direct cost). The

Question:

A task is expected to take 20 hours of labor at $25 per hour (direct cost). The required material cost is $500. The organization adds a fee of 30% to all direct labor costs to account for overhead. It does not add any fee on top of material costs. The total task cost is:
a. $500
b. $1,150
c. $1,250
d. $1,300