A total of 7000 stampings must be produced in the press department during the next three days.

Question:

A total of 7000 stampings must be produced in the press department during the next three days. Manually operated presses will be used to complete the job and the cycle time is 27 sec. Each press must be set up before production starts. Setup time for this job is 2.0 hr. How many presses and operators must be devoted to this production during the three days, if there are 7.5 hours of available time per day?