An industrial park is being planned for a tract of land near the river. To prevent flood
Question:
Embankment Height
Above Roadway (m) Initial Cost
2.0 ............................... $100,000
2.5 ................................ 165,000
3.0 ................................ 300,000
3.5 ................................ 400,000
4.0 ................................ 550,000
The embankment can be expected to last 50 years and will require no maintenance. Whenever the flood water flows over the embankment, $300,000 of damage occurs. Should the embankment be built? If so to which of the five heights above the roadway a 12% rate of return is required?