An industrial park is being planned for a tract of land near the river. To prevent flood

Question:

An industrial park is being planned for a tract of land near the river. To prevent flood damage to the industrial buildings that will be built on this low-lying land, an earthen embankment can be constructed. The height of the embankment will be determined by an economic analysis of the costs and benefits. The following data have been gathered.
Embankment Height
Above Roadway (m) Initial Cost
2.0 ............................... $100,000
2.5 ................................ 165,000
3.0 ................................ 300,000
3.5 ................................ 400,000
4.0 ................................ 550,000
An industrial park is being planned for a tract of

The embankment can be expected to last 50 years and will require no maintenance. Whenever the flood water flows over the embankment, $300,000 of damage occurs. Should the embankment be built? If so to which of the five heights above the roadway a 12% rate of return is required?

Fantastic news! We've Found the answer you've been seeking!

Step by Step Answer:

Related Book For  book-img-for-question

Engineering Economic Analysis

ISBN: 9780195168075

9th Edition

Authors: Donald Newnan, Ted Eschanbach, Jerome Lavelle

Question Posted: