Annie is planning a large surprise party for her sister Gwendolyn. She has developed the plan below,
Question:
a. Annie is most interested in reducing the time associated with creating the guest list. What is the crash cost per hour for that activity?
b. Annie will save $40 for every hour she can reduce from her plan. Annie has decided to crash her project and use the money she saves to purchase a larger gift for Gwendolyn. Which activity should she crash first?
c. Annie has now crashed activity A by four hours at a cost of $110. What other activity could she crash to further reduce the project?
d. Annie has now crashed activity A by four hours at a cost of $110 and activity E by two hours at a cost of $75. What other activity could she crash to further reduce the project?
e. How much money did Annie save by crashing the project?
f. What is the duration of the fully crashed project?
Step by Step Answer:
Managing Operations Across the Supply Chain
ISBN: 978-0078024030
2nd edition
Authors: Morgan Swink, Steven Melnyk, Bixby Cooper, Janet Hartley