Question: Assume that the activity time estimates (in days) for the swimming pool construction project in Problem 11 are as follows: a. What are the critical
Assume that the activity time estimates (in days) for the swimming pool construction project in Problem 11 are as follows:
.png)
a. What are the critical activities?
b. What is the expected time to complete the project?
c. What is the probability that the project can be completed in 25 or fewerdays?
n 667063005 T 546942884 325721563 Activity tiv ABCDEFGHI
Step by Step Solution
3.31 Rating (160 Votes )
There are 3 Steps involved in it
a Activity Expected Time Variance A 483 025 B 400 044 C 600 011 D 883 025 E ... View full answer