Balfour's is considering building a plant in one of three possible locations. They have estimated the following
Question:
Location Fixed Cost Variable Cost
Waco, Texas.....................$300,000........................$5.75
Tijuana, Mexico................$800,000........................$2.75
Fayetteville, Arkansas.........$100,000.......................$8.00
For what unit sales volume should they choose each location?