Balfour's is considering building a plant in one of three possible locations. They have estimated the following

Question:

Balfour's is considering building a plant in one of three possible locations. They have estimated the following parameters for each location:
Location Fixed Cost Variable Cost
Waco, Texas.....................$300,000........................$5.75
Tijuana, Mexico................$800,000........................$2.75
Fayetteville, Arkansas.........$100,000.......................$8.00
For what unit sales volume should they choose each location?
Fantastic news! We've Found the answer you've been seeking!

Step by Step Answer:

Related Book For  book-img-for-question
Question Posted: