Barbara Gordon, the project manager for web Ventures, Inc., compiled a table showing time estimate for each

Question:

Barbara Gordon, the project manager for web Ventures, Inc., compiled a table showing time estimate for each of the company’s manufacturing activities of a project, including optimistic, most likely and pessimistic,

a. Calculate the expected time, te for each activity.

b. Calculate the variance, Ï­2 for each activity

Barbara Gordon, the project manager for web Ventures, Inc., comp