Bradley Solutions and Alexander Limited are two well- established suppliers of inexpensive tools. Weekend Projects is a
Question:
a. Which of the two suppliers would provide the lowest annual cost to Weekend Projects? What shipping quantity would you suggest?
b. Before management could make a decision, another option became available. Zelda Tools offered the tool set for only S$.00 however, the lead time is longer than the other two suppliers. Zelda is a new supplier and has not been in the industry very long. Additional data for Zelda are in the second table. Management has begun to assess the administrative costs to manage the contract with Zelda. What is the lowest level of administrative costs at which Weekend Projects would be nu between using Zelda versus the option you chose in parta?
Step by Step Answer:
Operations management processes and supply chain
ISBN: 978-0136065760
9th edition
Authors: Lee J Krajewski, Larry P Ritzman, Manoj K Malhotra