Chihooli manufactures radiation-shielding glass panels. Suppose Chihooli is considering spending the following amounts on a new TQM

Question:

Chihooli manufactures radiation-shielding glass panels. Suppose Chihooli is considering spending the following amounts on a new TQM program:
Strength-testing one item from each batch of panels.................................. $65,000
Training employees in TQM...................................................................... 30,000
Training suppliers in TQM .................................................................... 40,000
Identifying preferred suppliers who commit to
on-time delivery of perfect quality materials................................................. 60,000
Chihooli expects the new program to save costs through the following:
Avoid lost profits from lost sales due to disappointed customers............. $90,000
Avoid rework and spoilage...................................................................... 55,000
Avoid inspection of raw materials........................................................... 45,000
Avoid warranty costs .............................................................................. 15,000
Requirements
1. Classify each item as a prevention cost, an appraisal cost, an internal failure cost, or an external failure cost.
2. Should Chihooli implement the new quality program? Give your reason.
Exercises (Group B)
Fantastic news! We've Found the answer you've been seeking!

Step by Step Answer:

Related Book For  book-img-for-question

Managerial Accounting

ISBN: 978-0176223311

1st Canadian Edition

Authors: Karen Wilken Braun, Wendy Tietz, Walter Harrison, Rhonda Pyp

Question Posted: