Complete the following MRP matrix for Item X. Determine when orders should be released and the size

Question:

Complete the following MRP matrix for Item X. Determine when orders should be released and the size of those orders.
LLC: 0 Item: X Period LT: 2 Lot Size: Min 50 Gross Requirements 25 30 56 25 100 40 30 20 Scheduled Receipts 50 Projected

Release orders in periods 1 through 5 for quantities of 50, 50, 56, 50, and 50 respectively. Please include/show work on how problem was solved.