Consider the following network for a small maintenance project (all times are in days; network proceeds from

Question:

Consider the following network for a small maintenance project (all times are in days; network proceeds from node 1 to node 7):

a. Draw an arrow diagram representing the project.

b. What is the critical path and associated time?


Consider the following network for a small maintenance project (


c. What is the total slack time in the network?
d. What is the expected time for 68, 95, and 99 percent completion limits?
e. If activity G had an estimated time of fifteen days, what impact would this have on your answer to partb?