Question: Consider the following project network and activity times (in weeks): a. Identify the critical path. b. How much time will be needed to complete this
Consider the following project network and activity times (in weeks):
.png)
a. Identify the critical path.
b. How much time will be needed to complete this project?
c. Can activity D be delayed without delaying the entire project? If so, by how many weeks?
d. Can activity C be delayed without delaying the entire project? If so, by how many weeks?
e. What is the schedule for activityE?
Finish Start ActivitvIA B C D E F G H Time 5 37 6 7 3 108
Step by Step Solution
3.52 Rating (166 Votes )
There are 3 Steps involved in it
a Critical path ADFH b 22 weeks c No it is a critical activity d Y... View full answer
Get step-by-step solutions from verified subject matter experts
Document Format (1 attachment)
148-M-S-Q-M (36).docx
120 KBs Word File
