Consider the playkool storage studio below. We wish to design an assembly line to assemble several units.
Question:
The parts are to be assembled according to the following precedence network:
a. Calculate the cycle time if 75 units per hour are to be assembled.
b. What is the minimum number of workstations?
c. Using your answer to part a, perform assembly-line balancing using €œAssign the task with the longer time€ heuristic rule, breaking any ties using €œAssign the task with the most followers€ rule. If there is still a tie, break it randomly.