Did Superiors October delivery breach the contract? R. J. Sanders, Inc., had a contract with the federal
Question:
R. J. Sanders, Inc., had a contract with the federal government to install the heating system at a federal prison camp. The company negotiated with Superior Boiler Works to purchase three large commercial units. On March 27, Superior sent a proposal to Sanders, offering to sell three boilers for a total of $156,000 and estimating time of delivery at four weeks. The parties exchanged further documents and held various discussions. Finally, on July 20, Sanders sent a “purchase order” for three boilers, agreeing to pay $145,827 and stating “Date required: 4 Weeks,” that is, August 20. On August 6, Superior sent a “sales order,” agreeing to sell the three boilers at that price, but providing a shipping date of October 1. This later delivery date forced Sanders to rent temporary boilers at a cost of $45,315. On October 1, Superior shipped the boilers, which arrived on October 5. Sanders sent a check in the amount of $100,000, claiming that Superior had delivered the boilers late and deducting the cost of its rental equipment. Superior sued for the additional $45,000 and moved for summary judgment, which the trial court granted. Sanders appealed, claiming that the contract had required Superior to deliver the boilers within four weeks.
Fantastic news! We've Found the answer you've been seeking!
Step by Step Answer:
Related Book For
Business Law and the Legal Environment
ISBN: 978-1111530600
6th Edition
Authors: Jeffrey F. Beatty, Susan S. Samuelson, Dean A. Bredeson
Question Posted: