DMD makes specialty bikes. The manager used to order enough bike parts for four months worth of
Question:
The manager heard about MRP, and wants to use it. DMD makes two types of bikes: Arrow and Dart. The manager wants to assemble 15 Arrow's and 10 Darts each week from weeks 4 through 8. The product structure trees for the two bikes follow.
He has collected the following information on lead times, inventory on hand, and lot-sizing methods (established by suppliers anchor DMD):
Scheduled receipts are:
Week 1: 20 Arrow's, 18 Ws
Week 2: 20 Darts, 15 Fs
Develop the material requirements plans for all the items.