Question:
Donner Racket Company manufactures two types of tennis rackets, the Junior and Pro Striker models. The production budget for March for the two rackets is as follows:
_________________Jounior ___________ Pro Striker
Production budget .. 18,000 units ........... 10,000 units
Both rackets are produced in two departments, Forming and Assembly. The direct labor hours required for each racket are estimated as follows:
_______________Forming Department ______________Assembly Department
Junior ............. 0.20 hour per unit .......................... 0.60 hour per unit
Pro Striker ....... 0.35 hour per unit .......................... 0.75 hour per unit
The direct labor rate for each department is as follows:
Forming Department .......................... $21 per hour
Assembly Department ......................... $16 per hour
Prepare the direct labor cost budget for March?
Step by Step Answer: