During March 2016, Garner Tool & Die Company worked on four jobs. A review of the direct

Question:

During March 2016, Garner Tool & Die Company worked on four jobs. A review of the direct labour costs reveals the following summary data:

During March 2016, Garner Tool & Die Company worked on

Analysis reveals that Job A257 was a repeat job. Job A258 was a rush order that required overtime work at premium rates of pay. Job A259 required a more experienced replacement worker on one shift. Work on Job A260 was done for one day by a new trainee when a regular worker was absent.
Instructions
Prepare a report for the plant supervisor on direct labour cost variances for March. The report should have columns for the following headings: (1) Job No., (2) Actual Hours, (3) Standard Hours, (4) Labour Quantity Variance, (5) Actual Rate, (6) Standard Rate, (7) Labour Price Variance, and (8) Explanations.

Fantastic news! We've Found the answer you've been seeking!

Step by Step Answer:

Related Book For  book-img-for-question

Managerial Accounting Tools for Business Decision Making

ISBN: 978-1118856994

4th Canadian edition

Authors: Jerry J. Weygandt, Paul D. Kimmel, Donald E. Kieso, Ibrahim M. Aly

Question Posted: